Project Management
14 projects · 3 delayed · 2 on hold · Last updated 06 Jun 2026
14
Total Projects
9
Active
3
Delayed
Avg 18 days behind
2
On Hold
4
Completed FY26
Active Milestone Tracker
OMR Phase 2 — Sholinganallur
Structural Work · PM: Anand Kumar
→ Floor 9 Slab Casting
Velachery Heights — Phase 1
Finishing & MEP · PM: Suresh Prabhu
→ Electrical Wiring — Block A
Perungudi Residences
Structural — DELAYED · PM: Karthik Raj
→ 3rd Floor Slab — 12 days behind
Medavakkam Villas — Phase 2
Pre-Construction · PM: Vijay Shankar
→ DTCP Approval Pending
Today's DPR Status
06 Jun 2026OMR Phase 2
SubmittedFloor 9 column casting — 85% done
Velachery Heights
SubmittedElectrical conduit laying — Block A floors 3-5
Medavakkam Villas
SubmittedBrickwork — Villa units 21-28
Perungudi Residences
Submitted3rd floor shuttering — 60% complete
Sholinganallur Plots
Not SubmittedDPR not yet submitted for today
Tambaram Township
SubmittedPlastering — Block B floors 1-2
Showing 10 of 10 projects